“Richco provided an excellent product that was quick and easy to apply”

“Our Decking Strips were delivered on time and just as Richco said, they were very easy to install”

Fast Floor

Specifications

Area Coverage
Coverage area is approximately 3.7m² per 25kg at 3mm thick.

Curing Time
Richco Fast Floor will accept foot traffic after approximately 6 hours. Richco Fast Floor will be ready for full use after 24 - 36 hours when laid at depths between 3 - 5mm. These curing times are based on a constant temperature of 15 - 20°C. Do not apply at temperatures lower than 5°C or higher than 30°C.

Surface Preparation
Concrete should be reasonably clean and free of loose surface material. A good sweep with a stiff broom is usually sufficient. Remove heavy oil and grease contamination using a degreasant. It does not matter if the concrete is damp.

Priming
Two primers are supplied. Dampen areas of bare concrete with clean cold water and leave for 20-30 minutes. Apply Primer 1 to the prepared surface using a brush or soft broom and allow it to soak into the concrete for at least 15-20 minutes. Primer 1 can be left overnight to dry if time permits. Primer 2 can be applied whilst Primer 1 is still tacky or if Primer 1 has completely dried. Apply the primers reasonably evenly to avoid ponding on the surface.

Mixing
Empty the large bottle of resin into the bucket and gradually add the powders ensuring complete dispersion, stirring and blending using a slow speed drill fitted with a mixing blade. Continue mixing for approximately 3-5 minutes until an even colour is obtained. The mixed components should be used immediately.

Application
Pour the mixed components on to the wet Primer. Using a rectangular trowel spread the mixed components across the surface of the concrete at the desired thickness. It is not essential that trowel marks are removed at this stage. Immediately after application a spiked roller should be used to improve the finish and release any trapped air. Work the spiked roller uniformly across the surface rolling each area 3 or 4 times from different directions. The spiked roller should not be used more than 20 minutes after the product has been applied (less in warm or very dry conditions) as it will then start to cure and the roller marks will not disappear.

Application Tools
Apply Richco Flake Floor Coating using a rectangular trowel, spiked roller and a mixing blade for use with an electric drill.

Cleaning of Application Tools
Applicators should be washed in warm soapy water before the product starts to cure.